某地下工程施工合同约定,计划1月份开挖土方80000m,合同单价均为85元/m。至1月底,经确认实际开挖土方90000m,实际单价为72元/m,则该工程的...

作者: rantiku 人气: - 评论: 0
问题 某地下工程施工合同约定,计划1月份开挖土方80000m,合同单价均为85元/m。至1月底,经确认实际开挖土方90000m,实际单价为72元/m,则该工程的费用偏差(CV)为( )万元。
选项 A.117 B.-117 C.85 D.-85
答案 A
解析 费用偏差CV=BCWP-ACWP=90000*(85-72)=117万元。

猜你喜欢

发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.