土坝施工时分层上料,每层填土厚度约为()m,上料之后即碾压。A、0.3 B、0.4 C、0.5 D、0.6

作者: rantiku 人气: - 评论: 0
问题 土坝施工时分层上料,每层填土厚度约为()m,上料之后即碾压。
选项 A、0.3 B、0.4 C、0.5 D、0.6
答案 C
解析 新版教材29页:坝体坡脚线放出后,即可在坡脚线范围内填土。土坝施工时是分层上料,每层填土厚度约0.5m,上料后即进行碾压,为了保证坝体的边坡符合设计要求,每层碾压后应及时确定上料边界。各个断面上料桩的标定通常采用轴距杆法或坡度尺法。
发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.