问题 关于桥梁工程卸落支架顺序描述错误的是()
选项 A:满布拱架可从拱顶向拱脚依次循环卸落 B:连续梁宜从跨中向支座依次循环卸落 C:简支梁宜从支座向跨中依次循环卸落 D:悬臂梁应先卸挂梁及悬臂支架,后卸无铰跨内支架
答案 C
解析 卸落支架和拱架应按拟定的卸落程序进行,分几个循环卸完,卸落量开始宜小,以后逐渐增大。每一循环中在纵向应对称均衡卸落,在横向应同时一起卸落。简支梁、连续梁宜从跨中向支座依次循环卸落。
发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.