非承包人原因引起的工程量增减,该项工程量变化在合同约定幅度以内的,应()单价。A:相应调整B:执行合同C:重新核对D:双方协商

作者: rantiku 人气: - 评论: 0
问题 非承包人原因引起的工程量增减,该项工程量变化在合同约定幅度以内的,应()单价。
选项 A:相应调整 B:执行合同 C:重新核对 D:双方协商
答案 B
解析

猜你喜欢

发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.